After being successful in securing the winning bid we were given critical timescales that we had to work to. Firstly we reclaimed all of the R22 refrigerant, removed internal evaporators and external condensers. We removed all existing pipe work, drainage and electrical cables. Once all removed from site we set to work installing the new Danfoss condensers, Searle evaporators, new refrigerant pipe work, drainage and electrical cables.
All works were commissioned and completed within the timescale set.
Location
Edinburgh
Sector
Refrigeration
Feature
cold room
Manufacturer
Danfoss
Year
2017