Glasgow Kelvin College is the newest of Glasgow’s three regional further education colleges. Formed by the merger of John Wheatley, North Glasgow and Stow colleges in November 2013, Glasgow Kelvin has all the expertise, facilities and resources to ensure that students receive a high quality learning experience that will provide them with the skills and knowledge to enable them to compete in today’s challenging jobs market, or to move on to further, more advanced learning.
Cool & Easy employed a crane operator to safely remove the AHU (Air Handling Unit) from the buildings roof. Once the removal had been completed, we replaced the system with a modern Daikin AHU, along with LTHW pipework as well as the electrical and ventilation works.
Once the new AHU was in place and commissioned, we carried out thermal insulation to the duct work and LTHW pipe work. At this point the site was then handed back to the client.
The total project was carried out within budget, on time and to client’s satisfaction.
Location
Glasgow
Sector
Ventilation
Feature
LTHW Pipework, AHU Plant
Manufacturer
Daikin
Year
2018